Research by DoINeedAPermit Research Team · Updated May 2026
The Short Answer
Every ADU in Martinez requires a building permit, regardless of size or type. California's ADU laws (AB 881, SB 9, AB 68) override local zoning, but Martinez still issues and inspects the permit through its building department.
Martinez sits in Contra Costa County, where the Bay Area's strict zoning historically blocked ADUs — but state law now forbids local code from blocking or significantly delaying them. The city cannot require conditional-use permits, variances, or vesting-tentative maps for ADUs that meet state standards (AB 881). What's unique to Martinez: the city recently adopted an ADU ordinance (posted on its planning website) that aligns with state minimums and accepts pre-approved ADU plans from the state's 'ADU Program' if available. Unlike some Bay Area cities that layer extra setback or parking demands, Martinez has largely ceded ground to state law. You file directly with the Martinez Building Department (part of Community Development). The 60-day shot clock (per AB 671 for ADUs in single-family zones) applies here, though design review or habitat-plan items can pause the clock. If your ADU is detached and under 800 sq ft, or a garage conversion, Martinez uses a streamlined plan-review track — typically 4–6 weeks if plans are clean. The city also accepts owner-builder permits for ADU work if you pull trades separately for electrical and plumbing (licensed subcontractor required for those).

What happens if you skip the permit (and you needed one)

Martinez ADU permits — the key details

State law owns ADU zoning in California. AB 881 (effective 2020) and SB 9 (effective 2022) stripped cities of authority to ban ADUs or impose conditions that effectively block them. In Martinez, this means you cannot be denied a permit solely because your lot is zoned single-family residential, or because local voters dislike ADUs, or because your neighbors object. The city must process your ADU application within 60 days of a complete filing (per AB 671, Government Code 65852.2(d)). That said, Martinez can still enforce legitimate health-and-safety codes: egress windows (IRC R310), utilities (code-compliant separately metered or sub-metered), parking (the city has largely waived parking for ADUs under 750 sq ft if certain conditions are met), and setbacks (state law allows reduced setbacks for accessory units). If your proposal triggers environmental review (rare for ADUs), or if it sits in a habitat-sensitive area, the 60-day clock pauses, and you could see 90–120 total days. The key is filing a complete application: site plan showing setbacks and lot coverage, floor plan with egress, utility layout, and proof of separate water/sewer/electrical service or sub-meter arrangement.

Martinez's local ADU ordinance and pre-approved plans. The city published its ADU rules (check the Martinez Planning Division website for the latest Municipal Code chapter or ADU fact sheet). Importantly, if your ADU matches California's state-approved 'ADU Program' plans (available free from the Adaptive Reuse of Housing for Accessory Dwelling Units project or HCD), Martinez cannot reject it on design or setback grounds — it must be deemed ministerial, and you get the fastest possible review (often 2–3 weeks for plan check). Pre-approved plans are available for detached ADUs (400–800 sq ft), garage conversions, and junior ADUs. If you do NOT use a state-blessed plan, your proposal goes to standard plan review, where the city's planner checks setbacks, building coverage, parking, and egress. This adds 4–8 weeks. Owner-builders can file for ADU permits under California Business & Professions Code § 7044, but electrical work, plumbing, and mechanical must be done by licensed contractors or the property owner themselves (only if owner is a licensed electrician/plumber — rare). Most homeowners hire a contractor for these trades.

Setbacks, lot size, and the 'accessory' rule. Martinez uses a tiered setback table in its local ordinance. For detached ADUs, typical minimums are 5 feet from rear property line and 5 feet from side setback (lower than single-family house rules). For garage conversions or ADUs above a garage, setbacks are relaxed further — often zero feet if the structure already exists. There is NO minimum lot size mandated by state law, though the building site must be large enough to accommodate the ADU footprint, parking (if required), and utilities. Contra Costa County's soil is mixed: coastal Martinez has compacted bay silt and sand; inland hills have granitic and clayey soils. Detached ADUs require a foundation (IRC R401–R408): typically slab-on-grade with 12-inch footings in stable soils, or pilings in expansive clay. Your engineer or contractor will size it based on a soil report (often $500–$1,500). One surprise: AB 881 prevents the city from requiring the ADU lot to be larger than the main house lot — a state-law floor on local zoning tyranny. Parking is complex. Martinez MAY require one off-street parking space for an ADU up to 750 sq ft if the unit is within a half-mile of transit or a TOD zone; zero spaces if farther or in a very-low-income area. But many cities (and Martinez increasingly) have waived ADU parking entirely. Check the latest city planning memo or call the building department to confirm the current parking rule — it changes quarterly as state law updates.

Utilities, egress, and inspection. Every ADU must have code-compliant egress: one operable window per bedroom (min. 5 sq ft, 24-inch width/height, sill ≤44 inches — IRC R310.1) or a second door. Garage conversions must trap the garage egress door behind a 1-hour fire wall, so a separate entry door is usually mandatory. Utilities must be sub-metered or separately metered to the ADU so that water, sewer, and electric are billed individually (or to you as the property owner separately). This is not optional — it's a state law trigger (AB 68) and a local requirement in Martinez. You'll file a utility letter from the property owner and the water/sewer district (East Bay Municipal Utility District for Martinez) confirming the sub-meter or separate connection plan. Electrical must be on a separate breaker panel (not shared with main house). Once your permit is issued, inspections follow the standard sequence: foundation, framing, rough trades (electrical, plumbing, HVAC), insulation/drywall, final building, and utility sign-off. For a 600-sq-ft garage ADU, expect 5–7 inspections over 8–12 weeks. For a detached new-build, add 1–2 inspections (grading, soils compaction). The city provides an inspection checklist with the permit; you schedule each through the online portal or phone.

Timeline, costs, and owner-occupancy. A typical ADU permit in Martinez costs $3,000–$15,000 depending on the project scope. This breaks down as: base permit fee (flat ~$500–$800), plan-review fee (tiered on square footage, ~$1,000–$3,000), and impact/mitigation fees (rarely applied to ADUs, but can add $1,000–$5,000 if traffic or school impacts are flagged). Pre-approved plans reduce plan review time and fee by ~40%. Total timeline from application to construction start: 4–6 weeks for a pre-approved garage ADU, 8–12 weeks for a custom design. California's AB 68 also requires ADU owner-occupancy for the main house in certain circumstances — specifically, if you're creating a junior ADU (smaller, inside the main dwelling), the owner MUST occupy the main house. For detached ADUs, there is NO owner-occupancy mandate in state law (though local ordinance can require it; check Martinez's latest rules). If you plan to rent both the main house and ADU to tenants, a detached unit is safer legally. Your city building contact is the Community Development Department; they host an online permit portal for applications and inspection scheduling. Processing times are publishing: 60 days for ministerial (pre-approved plan) ADUs, 90–120 days for design-review ADUs.

Three Martinez accessory dwelling unit (adu) scenarios

Scenario A
Detached new ADU, 600 sq ft, rear yard, 1-car setback met, separate metered utilities — Alhambra neighborhood lot (0.25 acre)
You own a 0.25-acre (roughly 10,900 sq ft) single-family lot in Martinez's Alhambra neighborhood (inland, clay-silt mix, frost depth 12 inches). You want to build a small detached ADU behind the main house: 600 sq ft, one bedroom, separate meter. The lot size and setback (rear ADU sits 10 feet from property line, main house 15 feet away) both meet state AB 881 minimums and Martinez local code. You file a complete ADU application with a site plan (showing lot lines, main house, ADU footprint, parking, and utilities), floor plan with egress window, and a soil report (geotechnical engineer, ~$1,200). The city planner reviews in 3–4 weeks and approves ministerially (no design exceptions needed). If you use a state-pre-approved plan for a 600-sq-ft detached ADU, the review is even faster (2 weeks). You then obtain permits for the building structure ($800 base permit), electrical ($300), plumbing ($300), and mechanical ($200) — total ~$1,600. Plan-review fees: ~$1,200. Utility coordination with East Bay Municipal Utility District for a separate water/sewer meter: free to coordinate, but the meter installation itself is ~$2,000–$3,000 (split with the EBMUD). Soil report and engineer review: ~$1,500. Total pre-construction cost: ~$6,300–$7,500. Construction takes 3–4 months (foundation, framing, roof, rough trades, finish, final). Inspections: foundation (week 2), framing (week 4), rough trades (week 6), drywall (week 8), final building (week 12). No environmental review needed for detached ADU ≤800 sq ft on an existing residential lot.
Permit required | Pre-approved plan recommended | Separate water/sewer meter required | Geotechnical soil report ~$1,200–$1,500 | Utility meter setup ~$2,000–$3,000 | Total permit & plan review ~$2,800–$3,200 | Construction cost ~$80,000–$120,000 | Timeline 4–6 weeks approval + 12–16 weeks build
Scenario B
Garage conversion to ADU, 500 sq ft, existing 2-car garage, add second entrance door, owner-occupied main house — Vine Hill area
You own a 1960s home in Martinez's Vine Hill neighborhood (coastal silt loam, no frost concern, flood zone unknown). Your detached 2-car garage (500 sq ft, wood frame, no insulation) is a candidate for conversion to a 1-bedroom ADU. No new foundation work needed — the slab is intact. However, you must: (1) upgrade the garage door opening to a proper insulated wall with 1-hour fire separation from the main house, (2) add a separate entrance door on the side, (3) add windows for egress (one operable window, min. 5 sq ft), (4) run separate electrical panel, (5) add a half-bath and kitchenette (sink, range, refrigerator), (6) insulate walls and roof to current energy code, and (7) sub-meter water/sewer. You file a plan-check application with photos of the existing garage, a floor plan showing the new wall, egress window, and utilities. The city approves this in 4–6 weeks (standard review; not eligible for pre-approved status because it's a conversion with custom layout). You pull separate permits: building ($600), electrical ($300), plumbing ($400), mechanical ($200) — total ~$1,500 permit fees. Plan review: ~$800. Utility-meter coordination: free coordination, ~$2,000 install. Parking: the city likely requires 1 off-street space (you may be able to use existing driveway or carport), or request a waiver if you're within a transit corridor. No parking variance needed if you waive or comply. Construction scope is smaller than detached (8–10 weeks), but the fire-wall and egress work add complexity. Inspections: framing (new wall), electrical rough-in, plumbing rough-in, insulation/drywall, final building. Owner can pull permits if you're a licensed electrician/plumber for those trades; otherwise, hire subs. Total pre-construction cost: ~$4,500–$5,500.
Permit required | Existing garage foundation OK | Separate entrance door required | 1-hour fire wall between garage & main house | Egress window ≥5 sq ft required | Separate electrical panel required | Sub-meter for utilities required | Permit + plan review ~$2,300–$2,500 | Utility meter ~$2,000 | Construction cost ~$40,000–$75,000 | Timeline 4–6 weeks approval + 8–10 weeks build
Scenario C
Junior ADU (internal, 400 sq ft), carved from existing master-suite bonus room, owner must occupy main house — Martinez downtown area
You own a 1970s ranch in downtown Martinez (near Main Street, compact lot 0.15 acre, bay silt). Your house has an oversized master suite with a bonus room (400 sq ft) that you want to convert into a junior ADU (JADU, per SB 9 and AB 68). A JADU is a self-contained unit inside the main dwelling: separate entry, kitchenette (sink, range, fridge, no full kitchen), bathroom, and one bedroom. Key constraint: state law (AB 68) requires the property owner to occupy EITHER the main house OR the JADU — you cannot rent both to tenants. File a JADU application with a floor plan showing the separate entrance (wall off the master, add a door), kitchenette layout, and bathroom. No separate utility meter is needed for a JADU (it's internal); water and sewer share the main line. However, electrical must be on a separate breaker from the main house to allow meter separation if future owners want to sub-meter. Review timeline: 2–3 weeks (ministerial, no design exceptions). Permit + plan review: ~$1,000–$1,200 total. Owner-builder allowed for general construction, but hire licensed electrician for the breaker panel work (~$400–$600). Plumbing (moving the drain for the kitchenette sink) may require a licensed plumber (~$800–$1,200). Construction scope is light: framing a wall for the separate entry, moving or adding a kitchenette, possible bathroom reconfiguration. Timeline: 4–6 weeks. Inspections: framing, rough trades (electrical/plumbing), drywall/finish, final. No soil report needed (no new foundation). Parking: no requirement for a JADU (internal unit). Total pre-construction cost: ~$2,500–$3,500.
Permit required | Junior ADU — owner must occupy main house or JADU (not both rented) | Separate electrical breaker panel required | Shared water/sewer meter OK | No additional parking required | Permit + plan review ~$1,000–$1,400 | Electrical breaker work ~$400–$600 | Plumbing sub $800–$1,200 | Construction cost ~$20,000–$40,000 | Timeline 2–3 weeks approval + 4–6 weeks build

Every project is different.

Get your exact answer →
Takes 60 seconds · Personalized to your address

AB 881 and SB 9: How California state law overrides Martinez zoning

In 2020, California Assembly Bill 881 went into effect, stripping local governments of the power to ban accessory dwelling units in single-family zones. Before AB 881, Martinez could (and did) restrict ADUs to owner-occupied properties, require conditional-use permits, impose lot-size minimums, or simply deny permits. Post-AB 881, the city cannot do any of this for detached ADUs or garage conversions under 800 sq ft (or 850 sq ft if owner-occupied). SB 9 (effective 2022) extended these protections: you can split a single-family lot into two parcels, each with an ADU, without subdividing (if you occupy one unit). In Martinez, this means a property owner can build a detached ADU on a 0.25-acre lot — something the local zoning code would have forbidden five years ago.

What Martinez CAN still regulate: egress safety (windows per IRC R310), utilities (separate metering per AB 68), parking (now minimal or waived), setbacks (state-law minimums are low enough that most lots qualify), and building/fire code compliance (standard building department review). The city cannot apply 'design review' to an ADU that matches a state-approved plan; it must approve ministerially. Ministerial means the building department checks the box that the plan meets code, no discretion, no delays. However, if your ADU is over 800 sq ft, or sits on a lot under 2,500 sq ft, or triggers environmental thresholds (rare), design review may apply. The 60-day clock (AB 671) resets if the city deems your application incomplete; if it is complete, the city must issue or deny within 60 days. This has forced Martinez to streamline — the city now has a dedicated ADU intake form and a staff planner to ensure completeness checks are accurate.

On the ground in Martinez, this manifests in streamlined processing. The city's website now features a one-page ADU fact sheet (check the Planning Division page) listing what's needed: completed application, site plan, floor plan, proof of separate utilities, and owner ID. No conditional-use permit, no variance, no vesting tentative map. If you bring complete paperwork and use a state-blessed plan, you could have approval in 2–3 weeks. The practical effect: ADU applications in Martinez are moving faster than they did in 2018–2019, and the city is approving them at near 100% (only rejections are for incomplete filings or code violations like insufficient egress).

Utilities, sub-metering, and why separate water/sewer is non-negotiable

AB 68 (effective 2022) mandated that every ADU have separately metered utilities — water, sewer, and electric — OR be sub-metered within a single meter. The law was written to protect tenants from inflated utility bills (where a landlord bills a tenant for 'their share' of water without a meter) and to enable property-tax assessment (assessor offices tax ADUs based on separate utility service). In Martinez, this means you cannot share a single water meter between the main house and ADU. You must either (1) install a separate water meter through East Bay Municipal Utility District (EBMUD), or (2) install a sub-meter within your property's main meter (permitted, but sub-meters have accuracy issues and are less favored). EBMUD charges roughly $2,000–$3,000 for a new meter installation (one-time; then ~$40–$80/month service charge for the ADU). Sewer is bundled with water in most Bay Area utilities; you coordinate a single call to EBMUD, and they install one meter for both water and sewer. Electrical is simpler: you run a separate breaker panel in your main house and sub-meter the ADU, OR have the utility (Pacific Gas & Electric, PG&E) install a separate meter (cheaper, ~$500–$1,000 one-time; then the utility bills the ADU tenant directly).

On a garage conversion (Scenario B), you likely already have a water line running to the garage (for a hose or carwash). Tie-in the new ADU kitchen sink and bathroom to that line, have EBMUD install the sub-meter, and you're done — no trenching. On a detached ADU (Scenario A), you may need to trench from the main water meter to the ADU; budget $1,500–$2,500 for that if the distance is more than 50 feet. Plan-check staff will ask to see a utility letter from the plumber stating 'separate meter planned' or 'sub-meter location shown on drawing.' If you don't address utilities in your permit application, the city will issue a plan-review comment ('Provide separate utility plan') and pause the 60-day clock. This is the #1 reason for delays. Applicants who bring complete utility letters (signed by EBMUD, PG&E, or a licensed plumber) get through plan check 2–3 weeks faster. Some property owners try to avoid sub-metering ('We'll just share and bill separately') — do not do this. It's a code violation, and code enforcement can force removal if a complaint arises.

For owner-builders, note that California plumbing contractor licensing (B&P Code § 7044) allows property owners to do their own plumbing work if they obtain the permit and sign as the 'responsible managing employee.' However, the connection to EBMUD's main must be done by a licensed plumber or EBMUD contractor; you cannot do that yourself. Electrical is similar: you can do wiring inside your ADU if you pull a permit under your name and pass city inspections, but the meter install and PG&E connection must be done by PG&E or a licensed electrician. Most homeowners outsource to avoid the hassle; a licensed electrician charges ~$800–$1,200 for a full ADU electrical rough-in, plan-check sign-off, and meter coordination.

City of Martinez Community Development Department (Building & Planning)
Martinez City Hall, 411 Main Street, Martinez, CA 94553 (or check city website for direct building permit office address)
Phone: Search 'Martinez California building permit phone' or call main city line (925) 372-3500 and ask for Building Permits | https://www.ci.martinez.ca.us (check for 'Permit Portal' or 'Online Services'; exact URL varies — call to confirm active portal URL)
Monday–Friday, 8:00 AM–5:00 PM (verify on city website; hours may vary)

Common questions

Can I build a detached ADU on a small lot (under 5,000 sq ft) in Martinez?

Yes, if the lot meets minimum setbacks for an accessory unit (typically 5 feet rear, 5 feet side per Martinez code) and the ADU footprint fits. California state law (AB 881) does not impose a lot-size minimum for detached ADUs. However, you must have room for parking (often 1 space, though waivers are available) and utilities. Lots smaller than 0.15 acre become tight. Call the Martinez Community Development Department with your lot size and they can confirm feasibility in 5 minutes.

Do I need a geotechnical soil report for an ADU in Martinez?

For a detached ADU, yes — a basic geotechnical report ($1,200–$1,500) is required to design the foundation per IRC R401. The report tests soil bearing capacity and expansive-clay risk. Martinez is on bay silt and clay; expansive soils are rare but possible inland. For a garage conversion, you do not need a soil report if the existing garage slab is sound. For a junior ADU (internal), no soil report is needed. The city will ask for this during plan review; bring it upfront to avoid delays.

What is the owner-occupancy requirement for ADUs in Martinez?

State law (AB 881, AB 68) does not require owner-occupancy for detached ADUs or garage conversions. You can own the property and rent both the main house and ADU to tenants. However, for junior ADUs (internal ADUs, per SB 9 and AB 68), the property owner MUST live in either the main house or the junior ADU — you cannot rent both to unrelated tenants. Martinez follows state law, so check which type of ADU you're building.

How long does it take to get an ADU permit in Martinez?

If you file a complete application with a state-pre-approved plan, 2–3 weeks (ministerial). If you submit a custom design, 4–6 weeks (standard plan review). The state-mandated 60-day clock applies; if the city deems your application incomplete, the clock resets, so submit with all utilities, egress, and setback info upfront. Construction takes another 8–16 weeks depending on scope (garage conversion vs. detached new build).

Do I need parking for an ADU in Martinez?

Parking requirements for ADUs in Martinez have been relaxed under state law. Generally, the city requires one off-street space for an ADU under 750 sq ft if the unit is more than a half-mile from transit. If you're closer to downtown transit or in a low-income census tract, parking may be waived. Call the Community Development Department to check your specific lot. Many applicants request waivers and receive them.

Can I pull an ADU permit as an owner-builder in Martinez?

Yes. California Business & Professions Code § 7044 allows property owners to permit and build ADUs. However, electrical, plumbing, and mechanical work must be done by licensed contractors or by you if you hold the license. Most owner-builders hire subs for these trades. You pull the main building permit in your name and coordinate trades. The city inspects as usual. This saves roughly $500–$800 in contractor overhead, but adds time-management burden.

What egress requirements apply to an ADU garage conversion?

Per IRC R310.1, every bedroom needs one operable window (minimum 5 sq ft, 24-inch width, 44-inch max sill height) OR a second door. In a garage conversion, you cannot use the garage door as egress (it must be blocked with a 1-hour fire wall per IRC R302.6 for attached garages). You must add a separate exterior door on the side or rear of the converted space. This is non-negotiable; the city will flag it during plan check if missing.

How much does an ADU permit cost in Martinez?

Permit and plan-review fees typically run $2,000–$3,500 combined (base permit ~$600–$1,000, plan review ~$1,200–$2,500 depending on ADU size and complexity). Add utility-meter setup (~$2,000–$3,000 for separate EBMUD meter), engineering/soil report (~$1,200–$1,500 for detached), and contractor markups. Pre-construction soft costs total $4,500–$8,000. Construction itself (detached, 600 sq ft) runs $80,000–$120,000; garage conversion, $40,000–$75,000.

Does an ADU in Martinez trigger environmental review or habitat restrictions?

Rarely. ADUs under 800 sq ft on existing residential lots are typically categorically exempt from CEQA (California Environmental Quality Act) review. However, if your lot sits in a sensitive habitat area, creek corridor, or wetland (unlikely in Martinez proper, but check the city's GIS map), or if you're proposing a second ADU (splitting a lot), environmental review may apply. Call the Martinez Community Development Department to check your address against environmental overlays — takes 5 minutes.

Can I use a state-approved ADU plan for my Martinez project?

Yes, strongly recommended. California's 'ADU Program' offers free, pre-approved plans for detached ADUs (400–800 sq ft), garage conversions, and junior ADUs. Martinez must approve these plans ministerially, no design review, no delays. You can download plans from HCD's website or the Adaptive Reuse of Housing for ADUs project. If your site plan, utilities, and setbacks match the approved plan, you get faster approval (2–3 weeks vs. 4–6 weeks for custom design). This is the fastest path in Martinez.

Disclaimer: This guide is based on research conducted in May 2026 using publicly available sources. Always verify current accessory dwelling unit (adu) permit requirements with the City of Martinez Building Department before starting your project.