Research by DoINeedAPermit Research Team · Updated May 2026
The Short Answer
All ADUs in Modesto require a building permit. California Government Code 65852.2 and subsequent amendments (AB 68, AB 881) override Modesto's local zoning and parking rules, but you must still file with the city and pass inspections.
Modesto sits in California's Central Valley, where expansive clay soil and a high water table can affect ADU foundation design — a factor the city's plan reviewers will flag if you're building detached. But the bigger local story is this: Modesto's building department processes ADU permits on a 60-day state-mandated shot clock (AB 671), and the city has adopted a streamlined ministerial approval path for ADUs that comply with state law, meaning no discretionary hearings or design review if your project fits the box. The city's local code (adopted 2020+) allows detached ADUs up to 1,200 square feet, garage conversions, junior ADUs, and above-garage units — but only if the primary dwelling is owner-occupied OR (under AB 68 amendments) if you're in a specified area like a transit-oriented zone. Unlike some California cities that still fight ADUs, Modesto has accepted the state override and created a fast-track path: if your plans are complete and comply with Modesto's ADU design standards (setbacks, height, roof pitch), you'll get approved within the 60-day window. The catch: Modesto still requires separate utility meters (or approved sub-metering for water/gas) and will ask about parking if your ADU is in certain zoning districts — though state law says you can't be required to provide more than one space, and some areas are parking-exempt.

What happens if you skip the permit (and you needed one)

Modesto ADU permits — the key details

California state law (Government Code 65852.2, amended by AB 68, AB 881, SB 9) mandates that cities like Modesto approve ADUs ministerially — meaning without discretionary design review or conditional-use hearings — if they meet objective standards. Modesto's local code (Chapter 20 of the Municipal Code, adopted 2020) embraces this requirement and defines three ADU types: detached units up to 1,200 square feet, garage conversions, and junior ADUs (a smaller unit carved from the primary dwelling, max 500 sq ft). The city also allows above-garage ADUs. The state law removes Modesto's ability to impose discretionary zoning restrictions like "one ADU per lot" or "ADUs only in R-3 zones" — the city must approve your ADU if it meets the objective standards in their local code, period. This is a huge shift from pre-2017 practice, and it explains why Modesto's ADU approval rate is now 90%+ compared to 15% ten years ago. The building permit itself triggers the 60-day AB 671 shot clock from the day the city deems your application complete; if they don't deny you by day 60, you're deemed approved. In practice, Modesto's plan reviewers will ask for clarification on setbacks (front, side, rear — detached ADUs must meet the primary zone setbacks), height (35 feet in most zones, measured to the highest point including roof pitch), roof pitch (matching the primary dwelling, typically 4:12 or steeper), and utility connections (separate meters or approved sub-metering). The city does not have a separate ADU permit fee tier; you pay the standard building permit fee (1.5% of estimated valuation, with a $200 minimum) plus plan-review fees ($250–$400), plus a city planning application fee ($100–$200) if planning input is required. Total soft costs (plan prep, surveyor, engineering) run $2,000–$5,000; permit fees $300–$700; and construction inspection fees $500–$1,500 if there are change orders.

Modesto's local twist: the city requires pre-application meetings for detached ADUs, and they strongly recommend using the state's SB 9 pre-approved ADU plans or Modesto's own model designs (available on the city website). If you use a pre-approved plan that matches your lot, the plan-review timeline collapses to 7-10 days instead of the full 60 days. The city's website hosts a PDF checklist for detached ADUs that lists exactly what they need: site plan with setbacks and easements called out, floor plan, elevations (front and rear, with height callout), foundation plan showing soil bearing and any required piers or posts (important in the Central Valley where clay can shift), electrical one-line diagram, and a parking plan if the ADU is in a zone requiring it (though state law caps parking at one space, and some areas waive it entirely). Modesto's plan reviewers are trained on state ADU law and are generally responsive; they reject less than 10% of ADU applications for missing items (vs. 25-35% in cities that fight the state mandate). The city's planning director has published guidance confirming that detached ADUs do NOT require a discretionary hearing and that the 60-day clock applies to all ADU permit applications. Owner-builders are allowed under California Business & Professions Code § 7044, but electrical and plumbing work must be done by a licensed contractor or pulled by the owner with a trade-specific permit and rough/final inspections by the city electrician/plumber.

One surprise rule in Modesto that catches applicants: the city requires proof of separate utility service BEFORE building permit issuance. Water, gas, and electric must have separate meters, or you must submit a utility company letter approving sub-metering (a device that splits one meter into two billing units). Septic systems are rare in Modesto proper; most properties are on city sewer, and ADUs connect to the same main-line lateral but still need a separate meter at the city connection or a sub-metering agreement with the gas/water utilities. Southern California Gas and PG&E (the two utilities serving Modesto) typically approve sub-metering for ADUs within 2-3 weeks, but the city won't issue your permit until the utility company has stamped off. This is the #1 reason ADU permits get delayed: applicants assume they can sort utilities after permit issuance, and the city shuts it down. Your utility coordination should start in week 1, not week 5. For electrical, you'll need a separate panel or a sub-panel rated for the ADU load; NEC 690.12 and local amendments govern sub-panel bonding. Again, the city won't finalize the electrical permit until PG&E has inspected the service upgrade.

Setback and lot-size rules: Modesto allows detached ADUs on nearly any lot size if the primary dwelling already exists. There is no minimum lot size in the city code (unlike some California cities that grandfather old rules). For setbacks, the detached ADU must meet the same front, side, and rear setbacks as the primary dwelling zone. In R-1 (single-family residential, the most common zone in Modesto), that's typically 25 feet front, 5 feet side, and 15 feet rear. On a small urban lot (say, 5,000 sq ft), fitting a 1,000-sq-ft detached ADU within those setbacks can be tight, and the city's plan reviewers will measure carefully. Easements (utility, drainage, access) are common in Modesto, especially in older neighborhoods near the delta; they reduce buildable area and will limit ADU placement. Before you hire an architect, order a title report and survey to identify easements. The city's GIS mapping tool (Modesto's parcel map search) shows some easements but not all. Owner-occupancy: under AB 68 (effective Jan 2020), Modesto no longer requires the primary dwelling to be owner-occupied for ADU approval, UNLESS the ADU is in certain restrictive zoning overlays (historic preservation districts, for example). In most Modesto neighborhoods, you can rent out both the primary dwelling and the ADU to separate tenants. However, if your property is in the downtown historic district or a specific overlay, local rules may kick back in — check with the planning department at the pre-app meeting.

Timeline and inspection sequence: Modesto's 60-day shot clock starts when the city deems your application complete (typically day 2-5 after submittal, if your plans are clean). Week 1-2, you get initial plan-review comments; week 2-3, you resubmit marked-up plans. Week 4, the city issues a Conditional Approval (not final permit) pending utilities and final grading plan. Week 5-6, you confirm utilities and submit final grading; week 6-7, the city issues the full building permit. Construction typically takes 8-16 weeks depending on size and complexity. Inspections happen in sequence: foundation (before concrete pour), framing (before drywall), rough-in electrical/plumbing (before insulation), insulation and drywall, and final building inspection. A separate planning sign-off confirms compliance with setbacks, parking, and easements. Final electrical, gas, and water inspections by the city utilities happen at final. The entire process from pre-app to certificate of occupancy typically runs 5-7 months for a straightforward detached ADU, 8-10 months if there are resubmittals or soil/foundation issues (common in the clay-heavy Central Valley).

Three Modesto accessory dwelling unit (adu) scenarios

Scenario A
Detached ADU (600 sq ft, new construction, R-1 single-family lot in central Modesto, owner-occupied primary dwelling, clay soil)
You own a corner lot in central Modesto (near the University district), 7,000 sq ft, with an existing 3-bed primary home. You want to build a 600-sq-ft detached ADU in the rear yard to house your adult child rent-free or to generate supplemental income. Setback requirements: 25 feet front, 5 feet side, 15 feet rear (R-1 zone). Your lot is 60 feet wide and 115 feet deep. The detached ADU footprint is 30 feet x 20 feet (600 sq ft), oriented parallel to the rear property line. Rear setback: you're 18 feet from the rear line (compliant). Side setback: you're 8 feet from the side line (compliant). The site plan shows no easements crossing the backyard. Foundation design is critical here: Modesto's central area sits on expansive clay, which shifts seasonally. The structural engineer will recommend either a stem wall on grade beams spaced 4 feet apart (typical for clay) or a slab-on-grade with reinforcing mesh and a moisture barrier. Cost difference is negligible ($2,000–$3,000). You'll need a soils report (Phase I ESA) — Modesto's plan reviewers often request this if the primary dwelling is on a similar clay lot. Expected cost: $600–$1,200. Your architect submits the detached ADU package: site plan, floor plan (one bed, one bath, kitchen, living area), elevations (roof pitch 5:12, height 22 feet to ridge, matching primary home), foundation detail, electrical one-line (200-amp sub-panel fed from main panel in primary house), plumbing schematic (separate water and gas meters shown externally), and a parking plan (one space in driveway near ADU entrance, required in R-1 zone). Modesto's planning review takes 14 days (you used a state pre-approved plan template); no resubmittals. Utilities: you contact PG&E and the water department in week 2; both approve separate metering within 10 days. The city issues conditional approval in week 4. Foundation inspection happens on concrete pour day (day 25 of construction). Framing inspection at day 45. Rough electrical/plumbing/HVAC at day 60. Final building inspection at day 80 (after drywall, paint, flooring). Electrical final and water final at day 85. Certificate of occupancy issued day 90 from building permit. Total time from pre-app to CO: 20 weeks. Permit fees: $450 (building permit at 1.5% of $30,000 estimated value = $450 minimum). Plan review: $350. City planning app fee: $150. Total city fees: $950. Utility coordination and soils report: $2,000. Architect/engineer: $3,500. Grading and foundation work: $8,000. Construction: $65,000–$85,000 total (materials and labor, no permits). Total project cost: $79,450–$99,450 before soft costs.
Permit required | Modesto 60-day shot clock applies | Clay soil — soils report recommended ($600–$1,200) | Separate water, gas, electric meters required | Roof pitch must match primary (5:12 typical) | One parking space required in R-1 zone | Building permit $450 + plan review $350 + planning fee $150 | Timeline: 20 weeks pre-app to CO | No discretionary hearing | Standard inspections: foundation, framing, rough trades, final
Scenario B
Garage conversion (3-car to 1-car + 500-sq-ft junior ADU, downtown Modesto historic district overlay, primary dwelling owner-occupied)
You own a 1920s Craftsman bungalow in downtown Modesto, in the designated historic preservation district. The property is 5,500 sq ft with a detached 3-car garage (built 1970s, non-contributing to the historic district). You want to convert the garage into a junior ADU (a smaller unit carved from the primary dwelling) by connecting a 500-sq-ft addition to the primary home's second bedroom and converting it into a separate ADU unit with its own entrance, mini-kitchen, and bathroom. The historic district overlay adds a layer of complexity: the city requires architectural review if exterior changes are visible from the public right-of-way. However, a junior ADU located at the rear of the primary home and accessed through a side passage (not visible from the street) may be exempt from design review. You'll want to clarify this at the pre-app meeting. Junior ADU rules: the ADU must be inside the primary dwelling's footprint or directly attached (no detached junior ADUs). Your 500-sq-ft addition connects to the primary home via a breezeway, which counts as directly attached. The junior ADU is 1 bedroom, 1 bath, with a small kitchen (sink, cooktop, refrigerator — state law allows kitchenettes up to 120 sq ft in junior ADUs). Egress: the bedroom window must be a compliant emergency escape (IRC R310: min 5.7 sq ft opening, 20 inches wide, 24 inches high for residential). You'll use a horizontal sliding window with a low sill. Water/septic: Modesto is on city sewer and water. The junior ADU connects to the same main lateral as the primary home but gets a separate meter (or approved sub-meter). Gas and electric are on the primary panel with a dedicated sub-panel for the ADU (25-amp minimum per NEC). The city's historic preservation staff and building department must coordinate. Plan review package: site plan showing addition footprint, new exterior elevations (must match the primary home's architectural style — Craftsman), floor plan showing the new bedroom/bath/kitchen layout, utility diagram, egress window detail, and a historic-district design review checklist. Modesto's historic preservation office has published design guidelines for additions; you'll reference them in the narrative. Expected plan-review time: 21 days (slightly longer due to historic-district coordination, but no formal hearing required). The city may ask for exterior materials matching the primary home (wood siding, trim detail) — this is a typical historic-district request. No structural rejection expected if egress and utility details are clear. Timeline: pre-app (3 days) to conditional approval (21 days) to permit issuance (28 days) to construction start (day 35). Construction for an addition + interior conversion typically runs 10-12 weeks. Inspections: building lines and setbacks (day 10 of construction), foundation (day 20), framing and egress window (day 40), rough electrical/plumbing (day 60), insulation/drywall (day 75), final building and utility (day 90). CO issued day 95. Total time from pre-app to CO: 22 weeks. Permit fees: $520 (1.5% of $35,000 estimated value for the addition portion). Plan review: $400 (historic district adds $100). City planning: $150. Historic preservation review: $75 (one-time, non-refundable). Total city fees: $1,145. Architect/engineer: $5,000 (more involved due to historic compliance and structural addition). Utility coordination: $1,500. Construction: $80,000–$110,000 (addition build, interior conversion, egress window, kitchen, bath). Total project cost: $88,145–$118,145 before soft costs.
Permit required | Junior ADU (interior + attached addition) | Historic district overlay — design review required ($75) | Egress window detail critical (IRC R310) | Separate utility meter or sub-meter required | Roof pitch and siding must match primary home | Kitchenette only (max 120 sq ft) | Building permit $520 + plan review $400 + planning $150 + historic $75 | Timeline: 22 weeks pre-app to CO | Modesto's historic design guidelines apply
Scenario C
Above-garage ADU (800 sq ft, 2-bed, new construction, R-2 multi-family zone near downtown, non-owner-occupied primary dwelling allowed under AB 68)
You own a duplex (R-2 zone, near downtown Modesto) with two 2-bed rental units. You want to build an 800-sq-ft, 2-bed ADU above a new 1-car carport/garage (ground floor). The primary dwelling (the duplex) is not owner-occupied; both units are rented. Under AB 68 (effective 2020), Modesto must approve ADUs in R-2 and higher-density zones WITHOUT the owner-occupancy requirement, as long as the ADU itself is not restricted by local code. Since R-2 is a multi-family zone, the ADU is approved ministerially. The above-garage design is popular because it maximizes buildable area on tight urban lots and avoids rear-yard setback conflicts. Your lot is 4,000 sq ft (40 feet x 100 feet). The carport footprint is 12 feet x 20 feet; the ADU is built on top, 28 feet x 20 feet (560 sq ft per floor, but floor area calculation is 800 sq ft including the overhang for the carport cover). Setbacks in R-2: 15 feet front, 5 feet side, 15 feet rear. Your carport is 16 feet from the front line (compliant) and 6 feet from the side line (compliant). The ADU is directly above, so setbacks match. Height limit in R-2 (downtown area near the city's specified transit zone): 45 feet. Your ADU is 35 feet to the roof ridge — compliant. Parking: the one stall under the carport counts toward the R-2 zone's parking requirement (which the city may waive for ADUs under state law, but Modesto counts it anyway). The city also requires 0.5 guest parking spaces per unit in R-2; your carport space + one designated guest space in the duplex driveway = compliant. Structural: the carport foundation must support the weight of the ADU above. Steel columns with footings or concrete piers (depending on soil). Again, you'll order a soils report because the Central Valley's clay and variable compaction affect bearing capacity. The engineer will design for 5-10 ton loads per column (typical for 800-sq-ft wood-frame upper deck). Plan review package: site plan (showing carport, parking, setbacks, easements), floor plans (ground-floor carport + storage, upper-floor ADU layout with 2 bed, 1.5 bath, kitchen, living area), elevations (showing height, overhang, how upper floor integrates with adjacent duplex profile), structural detail for carport columns/footings, electrical one-line (200-amp sub-panel in the carport electrical room, fed from main duplex panel or its own service if the meter bank allows), plumbing schematic (separate water/gas meters on the exterior of the carport), and parking diagram. Modesto's plan review: 18 days (R-2 zones are routine, no historic overlay). Utilities: PG&E and water dept. approve sub-metering/separate service within 7-10 days. Conditional approval issued day 21. Permit issued day 30. Construction start: day 40. Inspections: soils/foundation (day 15 of construction), carport framing/columns (day 35), ADU framing (day 50), rough electrical/plumbing (day 70), drywall/final (day 100). CO issued day 110. Total time from pre-app to CO: 24 weeks. Permit fees: $620 (1.5% of $41,000 estimated value). Plan review: $375 (structural complexity adds cost). City planning: $150 (R-2 may require planning sign-off). Utility coordination: $1,800 (more complex utility routing for above-garage). Soils report: $900. Architect/engineer: $6,500 (above-garage is structurally more involved). Construction: $90,000–$130,000 (carport structure, ADU framing, finishes, HVAC for upper deck, separate utility ingress). Total project cost: $101,345–$141,345 before soft costs. This scenario highlights Modesto's embrace of AB 68: you can build a 2-bed ADU above a garage in a multi-family zone without owner-occupancy of the primary dwelling, and the city will process it ministerially — no conditional-use hearing, no discretionary design review (unless historic overlay applies, which it doesn't here). This is a huge advantage over cities that still impose discretionary overlays on ADUs.
Permit required | Above-garage ADU (2-bed, 800 sq ft) | R-2 zone — ministerial approval (no discretionary hearing) | AB 68 allows non-owner-occupied primary dwelling | Soils report required for carport bearing ($900) | Structural engineer required for carport columns ($3,000–$4,000 in design) | Separate utilities (water, gas, electric) required | Building permit $620 + plan review $375 + planning $150 | Timeline: 24 weeks pre-app to CO | Parking requirement: one stall under carport + 0.5 guest spaces

Every project is different.

Get your exact answer →
Takes 60 seconds · Personalized to your address

Why Modesto's ADU approval is faster than most California cities: the AB 671 shot clock and ministerial pathway

Central Valley soil and foundation implications: Modesto's central area sits on a mix of bay mud (near the delta) and expansive clay (further inland). Clay shrinks and swells with moisture, and the Central Valley's dry summers and wet winters create seasonal movement of 0.5-1 inch per year in some areas. This doesn't doom an ADU, but it requires the structural engineer to design for it. Typical solutions: grade beams (reinforced concrete beams at 4-foot centers) or a slab-on-grade with a moisture barrier and reinforcing mesh. Detached ADUs in clay areas almost always need grade beams or piers; the engineer's recommendation will be in the soils report. A Phase I Environmental Site Assessment (soils report) costs $600–$1,200 and takes 7-10 days. Modesto's building department doesn't mandate soils reports (they're not required by code), but plan reviewers often request them for detached ADUs on unfamiliar lots. If your primary home was built in the 1990s or later on the same lot, the original builder's soils report may still be in the property record (ask the previous owner). If available, you can reuse it and save the cost. Foothill areas (east of Modesto, toward the Sierra) have different soil — granitic, well-draining — and typically don't require soils reports. Coastal and bay-area properties near Modesto's western edge may have bay mud, which has low bearing capacity and requires driven piles or helical screws; these are rare but cost $5,000–$15,000 if required. Bottom line: budget $1,000–$2,000 for soils work and allow 2-3 weeks for it in your pre-construction phase.

Utility coordination and the separate-meter requirement: why utilities hold up ADU permits

Electrical sub-panel rules: if the ADU shares the main electrical service with the primary dwelling (common in garage conversions and above-garage builds), the ADU must have a dedicated sub-panel fed from the main panel. NEC 690.12 and California's Title 24 amendments govern this. The sub-panel must be rated for the ADU's load (typically 100-200 amps, depending on size and heating/cooling). The main panel must have capacity to feed the sub-panel; if the main panel is already at 80% utilization (common in older homes), the service might need an upgrade (200-amp main panel replacement, $2,000–$5,000). Modesto's city electrician will flag this during rough inspection. Plan ahead: have the primary dwelling's existing electrical panel evaluated before you finalize the ADU design. If an upgrade is needed, budget for it. Detached ADUs (new structure, no shared panel) need their own service entrance (a meter and panel fed from the main utility line or a secondary service). This is more expensive ($2,000–$4,000) but avoids coordination with the primary dwelling's panel. Modesto's electrical inspector requires the one-line diagram (circuit loadout by room/appliance) to be submitted with the building permit; the diagram must show the sub-panel or service entrance location and amperage. Without it, the permit will be incomplete.

City of Modesto Building Department
1010 10th Street, Suite A, Modesto, CA 95354
Phone: 209-577-5376 | https://permits.cityofmodesto.org
Monday–Friday, 8:00 AM – 5:00 PM (closed holidays)

Common questions

Do I need owner-occupancy for an ADU in Modesto?

No, not anymore. AB 68 (effective Jan 2020) removed Modesto's owner-occupancy requirement for ADUs. You can build an ADU on your rental property, and both the primary dwelling and ADU can be rented to tenants. However, if your property is in a historic preservation district or a specific overlay zone, local rules may impose additional restrictions — check with the planning department at your pre-app meeting.

What's the maximum size of an ADU in Modesto?

Detached ADUs: 1,200 square feet (or 65% of the primary dwelling's size, whichever is smaller). Garage conversions and above-garage units: same 1,200-sq-ft limit. Junior ADUs (interior additions): 500 square feet or 25% of the primary dwelling's size, whichever is smaller. If your primary home is 1,500 sq ft, the junior ADU can be max 375 sq ft. These limits are per Modesto's local code and California Government Code 65852.2.

How much will the ADU permit cost in Modesto?

Building permit fees are 1.5% of the estimated construction value, with a $200 minimum. For an $80,000 ADU project, expect $450–$500 in building permit fees. Plan review adds $250–$400. City planning application (if required): $100–$200. Utility coordination (separate metering or sub-meter approval): $500–$1,500. Total city/utility fees: $1,300–$2,600. Soft costs (architect, engineer, soils report, surveyor): $3,000–$8,000. Total pre-construction cost: $4,300–$10,600.

Can I use an owner-builder permit for an ADU in Modesto?

Yes, under California Business & Professions Code § 7044. You can be the owner-builder for an ADU if it's on your primary residence and you occupy or intend to occupy the property as your principal place of residence. However, all electrical work must be done by a licensed electrician or pulled under a homeowner's trade-specific permit and inspected by the city electrician. Plumbing and HVAC likewise require licensed contractors or trade-specific permits. General carpentry, painting, and finishes can be owner-built.

What happens if my ADU doesn't comply with Modesto's setback rules?

Modesto's building department will reject the permit if the ADU violates setbacks. However, you can apply for a variance (called an 'administrative variance' in California) if the setback violation is small (typically 1–2 feet). Variances require a separate application, a $500–$800 fee, and can take 6–8 weeks. Alternatively, you can redesign the ADU to comply with setbacks; most sites can accommodate a smaller footprint or repositioning. Discuss options at the pre-app meeting before hiring an architect.

Is parking required for an ADU in Modesto?

Parking requirements vary by zone. In R-1 (single-family), Modesto typically requires 1 parking space per ADU. In R-2 (multi-family), parking rules are set by zone and may be waived under state law (Government Code 65852.2 limits parking to 1 space per ADU and allows exemptions in certain areas, including transit-rich zones). Downtown Modesto may have reduced or waived parking for ADUs. Confirm at your pre-app meeting; the planning department will tell you the exact requirement for your lot.

How long does it take to get an ADU permit in Modesto?

Modesto's 60-day shot clock (AB 671) applies from the date the city deems your application complete. In practice, plan review takes 14–21 days if your design is clean. Utility approvals add 10–14 days. Conditional approval is usually issued by day 28–35, and final permit by day 35–45. Total time from pre-app to permit issuance: 6–8 weeks. Construction typically takes 10–16 weeks depending on size and complexity. Total time from pre-app to certificate of occupancy: 20–28 weeks.

What if I'm building an ADU in Modesto's historic district?

Historic district ADUs require design review by Modesto's historic preservation staff to ensure exterior compatibility (matching roof pitch, siding materials, window style, etc.). This adds 5–10 days to plan review and a $75–$150 design-review fee. Detached ADUs or additions on the rear of the lot (not visible from the street) may be exempt from design review — clarify this at pre-app. Attached ADUs (garage conversions, junior ADUs) are more likely to be exempt if interior-focused.

Do I need a soils report for a detached ADU in Modesto?

Modesto's code doesn't mandate soils reports, but the building department often requests them for detached ADUs, especially in clay-heavy areas (central Modesto). The Central Valley's expansive clay can shift 0.5–1 inch per year, and the engineer needs to size the foundation accordingly. Cost: $600–$1,200. Foothill properties (granitic soil) and properties where a soils report was done for the primary dwelling in the past 20 years may not need a new report — ask the planning department at pre-app.

Can I rent out an ADU in Modesto immediately after it gets a certificate of occupancy?

Yes, once the city issues a final certificate of occupancy, the ADU is approved for occupancy and rental. No deed restriction, rental license, or local tenant ordinance restricts ADU rental in Modesto (though California state law prohibits owner-move-in evictions of ADU tenants in certain circumstances — consult a local real estate attorney on that). You should obtain landlord insurance and follow Modesto's standard rental regulations (local ordinance Chapter 20 covers fair housing, but ADU-specific restrictions are minimal).

Disclaimer: This guide is based on research conducted in May 2026 using publicly available sources. Always verify current accessory dwelling unit (adu) permit requirements with the City of Modesto Building Department before starting your project.