Research by DoINeedAPermit Research Team · Updated May 2026
The Short Answer
A full kitchen remodel in Aventura requires building, plumbing, and electrical permits if you move walls, relocate fixtures, add circuits, modify gas lines, or vent a range hood to the exterior. Cosmetic-only work—same-location cabinet/countertop swap, appliance replacement on existing circuits—is exempt.
Aventura's Building Department enforces Florida Building Code (FBC) adoption of the 2020 International Residential Code, but the city has added specific requirements that differ from neighboring jurisdictions. Most notably, Aventura requires a separate Plumbing Permit Application and Electrical Permit Application for kitchen work—they don't bundle these into a single building permit like some Florida municipalities do. The city also enforces stricter kitchen-exhaust termination rules: range-hood ducts must terminate through an exterior wall with a cap detail shown on plans, and many inspectors require a mechanical-load calculation if the duct run exceeds 25 feet. Because Aventura sits in FEMA flood zone AE (high-risk coastal), kitchens in homes with elevated first floors trigger additional flood-elevation verification on any plumbing work. Lead-paint disclosure (ORR Form) is required for any home built before 1978 touching walls or trim. The city's online permit portal (through its website) allows real-time status tracking, but in-person plan review still happens at city hall on Aventura Boulevard—no expedited over-the-counter plan review for kitchens. Expect 3–5 week turnaround for full review, not 3 weeks.

What happens if you skip the permit (and you needed one)

Aventura full kitchen remodel permits — the key details

Aventura requires THREE separate permits for most full kitchen remodels: Building (structural/framing/drywall), Plumbing, and Electrical. If you're adding or relocating a range hood with exterior ducting, you may also trigger a Mechanical permit—the Building Department's permit-intake staff will tell you which combination is needed once you file the intake form. The city enforces the 2020 FBC, which adopts the 2020 International Residential Code (IRC) with Florida amendments. The most critical rule: any wall removal or bearing-wall modification requires a signed engineer's letter (per IRC R602.10) and a structural-design plan showing the proposed beam, reactions, and foundation support. The city's chief building official or their delegate must approve the engineer's letter BEFORE framing inspection—submitting an engineer's letter with your plans is not optional, it's a prerequisite. Load-bearing wall identification is the #1 reason for plan rejections in Aventura kitchens. If you're unsure which walls are load-bearing, a structural engineer will cost $300–$500 for a stamped letter; if you proceed without one and a wall is load-bearing, the city will issue a stop-work order and demand removal of unsupported framing. Aventura also enforces stricter-than-average documentation for kitchen-exhaust venting: the range-hood duct must terminate through an exterior wall (not the roof or into an attic), and your electrical plan must show the location of the hood, duct route, termination point, and a 4-inch diameter cap detail. Many inspectors request that you submit a photo of the termination point during rough inspection.

Plumbing changes in Aventura kitchens are heavily scrutinized because of coastal floodplain concerns. Per Florida Building Code Section 405, kitchens in flood zones must have any plumbing fixtures elevated above the base flood elevation (BFE) or have a compliant wet-venting system. If you're relocating a sink, dishwasher, or ice-maker line, your plumbing plan must show the trap-arm, the vent-stack routing, and confirmation that the vent connects to an existing vent within 5 feet (IRC P2704.1). Sinks in Aventura kitchens require a trap clearance of at least 18 inches from the underside of the counter to allow for proper venting and future service; many countertop-island remodels fail inspection because the trap arm is too steep or the vent is too short. The city's plumbing inspector will request a cutaway cross-section of under-sink plumbing if the layout is unusual. If you're moving the sink away from the existing plumbing rough-in, you'll need to either extend supply lines and the drain-vent system (expensive) or relocate the rough-in before the pour (requires coordination with the builder or prior approval). Aventura requires that all supply lines in kitchen areas be concealed in walls or soffit cavities; exposed PEX under counters is not permitted. For dishwasher drainage, the city enforces a high loop or a check valve on the drain line; a straight slope from the dishwasher to the sink drain is not compliant and will be cited during rough inspection.

Electrical work in Aventura kitchens is governed by the 2020 National Electrical Code (NEC) as adopted by Florida. The biggest pain point: IRC E3702 and NEC Article 210 mandate TWO separate small-appliance branch circuits (20 amp, GFCI-protected) serving the kitchen counter receptacles—one circuit must serve only countertop outlets, the other can serve the refrigerator or island outlets. If your kitchen doesn't have two separate 20-amp circuits, you must add them. Many DIY remodelers and even some unlicensed electricians miss this rule, and it's the #1 reason for electrical-plan rejections in Aventura. Counter-top receptacle spacing must not exceed 48 inches between outlets (measured along the countertop edge), and EVERY countertop receptacle and the dishwasher outlet must be GFCI-protected (per NEC 210.8). The electrical plan you submit must show every outlet location, the breaker panel diagram with circuit numbers and amperage, and the GFCI layout. If you're adding a new 240-volt circuit for an electric range or wall oven, you'll need a dedicated 40-50 amp circuit routed directly from the main panel; the city will inspect the breaker, wire gauge, and terminal connections. Aventura's electrical inspector is unusually strict about conduit fill and wire routing—if you're running multiple circuits through a single 3/4-inch conduit, the inspector may reject it for exceeding 40% fill capacity (NEC 300.17). If you're adding recessed lighting, the city requires IC-rated (insulated-contact) fixtures if they're within 3 inches of insulation; non-IC fixtures in standard attic insulation is a code violation. Any new electrical work requires a licensed Florida electrician—Aventura does NOT allow unlicensed owner-builder work on electrical circuits, even if you're the homeowner. (See Florida Statutes Section 489.103 and Aventura's local amendments.) If you hire an unlicensed electrician or attempt it yourself, the city can fine you $500–$1,000 and demand removal of all unpermitted work.

Gas-line changes in kitchens are regulated by IRC G2406 and Florida Building Code Chapter 24. If you're relocating a range or adding a gas cooktop, the gas supply line must be either black iron, CSST (corrugated stainless steel), or copper tubing certified for gas—PVC, PEX, and garden hose are not permitted. The gas line must terminate in a shutoff valve within 18 inches of the appliance, and the appliance must be secured to the floor or cabinet per manufacturer specs. Aventura requires a licensed gas fitter (Class B natural-gas contractor) to certify the gas-line work; homeowners cannot legally install or modify gas lines themselves. If you're moving the gas line more than 3 feet, you'll need a separate natural-gas-permit application from the city. The inspector will perform a pressure test (typically 3 psi for 15 minutes) and a soapy-water test on all fittings before you can turn on the gas. If you're installing a new range hood with a gas cooktop underneath, the hood-damper must open automatically when the burners are lit; this coordination is shown on the mechanical plan. Cost of gas-line relocation is $800–$2,000 depending on distance and obstacles.

Timeline and inspection sequence in Aventura: After you file permits with the Building Department, expect 3–5 weeks for plan review (the city doesn't offer expedited review for kitchens). Once plans are approved, you'll schedule inspections in this order: (1) Rough plumbing (before walls are closed), (2) Rough electrical (before drywall), (3) Framing (if any walls were moved—the engineer's letter and beam details are verified here), (4) Drywall/final framing, (5) Final plumbing, (6) Final electrical, (7) Final building (overall inspection). Each inspection must pass before the next one is scheduled; if an inspection fails, you'll pay a re-inspection fee ($75–$150 per sub) and wait another week. The city's inspector can be reached through the permit portal, and most inspections are scheduled 24–48 hours in advance. If you're adding mechanical (range hood), you'll also have a rough mechanical and final mechanical inspection—that's 9 total inspection points. Plan for 6–8 weeks of calendar time from permit issuance to final sign-off, assuming no rejections. If your plans are rejected on first submission, add another 2–3 weeks for resubmission and re-review.

Three Aventura kitchen remodel (full) scenarios

Scenario A
Countertop, cabinet, and appliance replacement—same plumbing location, new range hood vented to exterior, no walls moved (Aventura Hills neighborhood)
You're pulling out the old kitchen, replacing all cabinets and countertops on the existing footprint, installing a new electric range, dishwasher, and refrigerator, and adding a new 30-inch range hood that vents through the exterior wall above the cooktop. The sink stays in the same location. This is a common 'refresh' that many homeowners think is cosmetic—but the range-hood venting triggers a Building Permit and a Mechanical Permit. Why? Because cutting a hole in the exterior wall to accommodate the duct—whether it's 4 inches in diameter or larger—requires structural verification (IRC R602) and code approval of the termination detail. Aventura's building inspector will want to see the range-hood model number, duct diameter, routing diagram (how the duct gets from the hood to the wall cavity to the exterior), and a photo or detail drawing of the cap. Cost: approximately $12,000–$18,000 for the cabinets, countertops, and appliances combined; permits are roughly $400–$600 (two permits at $200–$300 each). Electrical sub-permit not required because the new range is replacing the old one on the existing circuit (assuming it's a dedicated 240-volt circuit already in place—if not, you'll need a third electrical permit). Plumbing sub-permit is not required because the sink and dishwasher stay in place. Inspections: (1) Framing (to verify the hood-duct opening is correctly sized and doesn't compromise structural members), (2) Rough mechanical (to verify duct routing and damper installation), (3) Final building (to confirm the exterior cap is installed correctly). Timeline: Permits issued in 3 weeks, inspections scheduled in 5–7 business days after each phase, final sign-off 2 weeks after rough mechanical. No engineer's letter required because no walls are touched. Flood-elevation work: Aventura is in flood zone AE; if your kitchen is above the BFE, no additional work is required. If below, verify the range and dishwasher openings comply with the wet-dry demarcation line—the inspector will check this during final.
Two permits (Building + Mechanical) | $400–$600 in permit fees | Licensed contractor required for range-hood installation | $12,000–$18,000 total project cost | Framing + rough mechanical + final inspections
Scenario B
Removing non-load-bearing wall between kitchen and dining room, relocating sink 8 feet, adding new dishwasher location, new 20-amp small-appliance circuits (Turnberry Isle neighborhood)
You want to open up the kitchen to the dining room by removing the wall between them. The sink is currently on the far kitchen wall and you want to move it to a new island; the dishwasher location also shifts 10 feet. You're adding two new countertop receptacles and a dishwasher outlet, which requires new 20-amp branch circuits (the old kitchen only has one small-appliance circuit). This scenario requires ALL THREE permits: Building (wall removal + framing), Plumbing (sink relocation + new drain/vent), and Electrical (new circuits). Before you file, you must have a structural engineer verify that the wall is non-load-bearing. Most kitchens in Aventura built after 1980 have non-load-bearing partition walls, but some older homes have load-bearing kitchen walls that support the roof or second floor—if the engineer determines it IS load-bearing, you'll need a structural design for a beam (add $1,500–$3,000). Assuming it's non-load-bearing, the engineer's letter costs $300–$500. The plumbing relocation is the tricky part: you'll need to relocate the supply lines (hot and cold) 8 feet to the new sink location and reroute the drain and vent stack. If the new island sink can't tie into the existing vent within 5 feet, you may need to run a new vent through the roof—inspect code requires the vent to terminate at least 12 inches above the roof surface and 3 feet from any roof penetration (IRC P3103). The new dishwasher location also requires a new supply and drain connection; if there's no existing hot-water line nearby, you'll run PEX supply lines through the wall cavity. Cost of plumbing relocation: $2,000–$4,000 (materials + labor + new rough-in framing). Electrical: You're adding two new 20-amp circuits routed from the main panel to countertop outlets and the dishwasher. If your main panel is far from the kitchen, the electrician may need to run new Romex (14/2 or 12/2 depending on circuit length) through the wall cavities, which requires opening drywall during rough-in and patching after trim. Cost: $1,500–$2,500 for electrical rough-in and trim. Permits and fees: Building ($250–$400), Plumbing ($250–$400), Electrical ($300–$500) = $800–$1,300 total. Inspections: (1) Framing (verify wall removal doesn't compromise roof or second-floor load), (2) Rough plumbing (verify new drain/vent layout, trap clearance, high loop on dishwasher), (3) Rough electrical (verify circuit routing, outlet locations, GFCI protection), (4) Drywall/final framing, (5) Final plumbing (confirm all connections tight, no leaks during pressure test), (6) Final electrical (verify all outlets and circuits are GFCI, breaker is correct amp), (7) Final building. Timeline: 4–6 weeks from permit issuance to final. If plans are rejected (common reason: vent-stack routing not shown clearly), add 1–2 weeks for re-review.
Three permits (Building + Plumbing + Electrical) | $800–$1,300 in permit fees | Engineer's letter required ($300–$500) | $2,000–$4,000 plumbing relocation | $1,500–$2,500 electrical circuits | 7 separate inspections | 4–6 weeks timeline
Scenario C
Full kitchen gut-remodel, removing load-bearing wall with beam, relocating gas range, adding new ductless range hood, converting vinyl flooring to tile (Aventura Park neighborhood)
This is a comprehensive kitchen overhaul: you're removing the existing kitchen wall to open to the living room, but the engineer confirms it IS load-bearing (supports the second floor or roof). You're replacing a gas cooktop with a new gas range in a different location, adding a ductless range hood (no exterior duct), installing new gas supply line, and replacing the flooring with large-format ceramic tile. This scenario showcases Aventura's most stringent requirements: load-bearing structural work, gas-line work, and moisture-management details specific to the coastal climate. The engineer's design must specify a beam (usually LVL or steel I-beam) sized to carry the load that the wall carried, along with proper reactions at each end and footing verification if the reactions exceed the existing post capacity. If the beam ends on new posts that don't tie to the foundation, the engineer must specify a concrete footing below the frost line—but Florida has no frost line, so the footing must extend into stable soil or limestone (typically 18–24 inches deep, verified by a geotechnical engineer for $500–$800). Aventura strictly enforces this because of the sandy and karst-limestone soils. Cost of structural design: $1,500–$3,000. The gas-line relocation requires a licensed gas fitter and a separate natural-gas-permit application; if the range is relocating more than 3 feet, expect the gas fitter to shut off the main supply, disconnect the old line, route a new CSST or black-iron line through the wall cavity, and terminate it within 18 inches of the new range location. The natural-gas inspector will perform a pressure test. Cost: $1,200–$2,000 including permit. The ductless range hood is a mechanical appliance (it has a motor and filter cartridge) but does NOT require a ductless-hood-specific permit in Aventura because it's recirculating (no exterior vent). However, the electrical circuit powering the hood must be included on your electrical plan. Flooring: Large ceramic tile over a new cement backer board substrate is compliant; the backer board must be installed per IRC R703 on a stable floor (verify the existing floor structure is not waterlogged or damaged before tiling). If you're removing old vinyl asbestos tile (VAT), which was common in kitchens built before 1980, you'll need an abatement contractor and a separate hazmat permit from Aventura—abatement typically costs $1,500–$3,000 and adds 2–3 weeks to the schedule. The city does NOT allow DIY asbestos removal. Permits required: Building, Plumbing, Electrical, Mechanical (for the gas range), and Natural Gas (separate application). That's FIVE permits. Fees: approximately $1,500–$2,500 total across all five. Inspections: (1) Structural framing (engineer present or inspector reviews stamped design), (2) Rough plumbing (if sink is relocated), (3) Rough electrical, (4) Rough mechanical (if gas range is new), (5) Framing/drywall, (6) Final plumbing, (7) Final electrical, (8) Final mechanical (gas range safety), (9) Natural-gas inspector (pressure test), (10) Final building (overall compliance, floor substrate, beam installation). That's 10 inspection points. Timeline: 6–8 weeks from permit issuance to final, or 10–12 weeks if asbestos abatement is required. Total project cost (labor + materials + permits + engineer): $45,000–$80,000 depending on finishes and whether structural contingencies arise. This is the most complex kitchen scenario and the one most likely to uncover code violations mid-construction (e.g., beam reactions exceed foundation capacity, gas-line routing conflicts with structural framing).
Five permits (Building + Plumbing + Electrical + Mechanical + Natural Gas) | $1,500–$2,500 permit fees | Engineer's structural design required ($1,500–$3,000) | Gas-line relocation + fitter license ($1,200–$2,000) | Possible asbestos-abatement hazmat permit ($1,500–$3,000) | 10 separate inspections | 6–12 weeks timeline | $45,000–$80,000 total project cost

Every project is different.

Get your exact answer →
Takes 60 seconds · Personalized to your address

Why load-bearing-wall engineering is non-negotiable in Aventura kitchens

Aventura sits on sandy soil with pockets of limestone karst (subsurface voids). When a load-bearing wall is removed without a properly designed and installed beam, the roof or second-floor load transfers to the remaining side walls and posts, which may settle unevenly or fail. The sandy soil doesn't provide uniform bearing, so even a small structural miscalculation can lead to diagonal cracks in drywall, foundation settlement, or—in worst case—partial collapse. The city's building official requires an engineer's letter before ANY load-bearing wall is disturbed. The engineer must site-verify the wall (walk the property, check if it aligns with load paths from above), pull property records or conduct a structural survey to confirm bearing status, and then design a beam (LVL, steel I-beam, or built-up lumber) with specified reactions at each end. If the reactions exceed the existing footer capacity, new footings must be excavated and installed below stable soil (typically 18–24 inches in Aventura). The city's structural inspector will photograph the footing before concrete is poured and again after the beam is installed. If you skip the engineer's letter and proceed with removal, the city will issue a stop-work order, demand removal of the wall or installation of an engineered beam, and assess fines up to $500 per day. Insurance claims on structural damage caused by unpermitted wall removal are typically denied. The engineer's fee ($1,500–$3,000) is a small price compared to the cost of fixing a failed beam or foundation settlement.

Coastal flood-zone plumbing: Aventura's AE-zone trap and vent requirements

Aventura is almost entirely in FEMA flood zone AE (coastal high-hazard area). Florida Building Code Section 405 and IRC R322 impose strict rules on plumbing in flood zones: any fixture below the base flood elevation (BFE) must either be elevated above BFE or must use a compliant wet-venting system. For kitchens, this means the sink trap and drain line cannot rest below BFE if the kitchen is in a flood-prone area. Most Aventura homes have finished first floors well above BFE, so this is rarely a practical constraint—but if your kitchen is in a basement or at-grade space, the plumbing rough-in must be verified against the FEMA flood-elevation map and the city's flood-elevations data (published on the city's website). If your kitchen IS below BFE, your plumbing plan must show either (a) all fixtures elevated above BFE with flexible connections, or (b) a certified wet-venting system (which is complex and rarely used for kitchens). The city's plumbing inspector will cross-reference your address against the flood-elevation database and will cite any non-compliant fixture placement. Additionally, Aventura requires that all below-BFE plumbing materials be marine-grade or corrosion-resistant (PVC for DWV, PEX for supply, or CPVC for supply in some cases)—galvanized steel supply lines are not permitted below BFE. The cost of ensuring compliance is typically $300–$800 in extra material and plan review, but getting it wrong can result in failed inspection and forced relocation of drain lines post-drywall, which is expensive and invasive.

City of Aventura Building Department
Aventura City Hall, 3000 Municipal Drive, Aventura, FL 33180
Phone: (305) 468-8800 (main line; ask for Building Department or Permits Division) | https://www.aventurfl.gov/permits (check city website for online permit status portal URL)
Monday–Friday, 8:00 AM–5:00 PM (verify holiday closures on city website)

Common questions

Do I need a permit to just replace my kitchen cabinets and countertops if I'm not moving the sink?

No, not if you're keeping the sink in the same location and not adding electrical circuits or changing any appliances. Cosmetic cabinet and countertop replacement is exempt from permitting. However, if you're adding a new range hood vented to the exterior, a new dishwasher, or new electrical outlets, you'll need permits. The safest approach is to call the Building Department intake line and describe your exact scope before starting—they can confirm permit requirements in 2–3 minutes.

What's the difference between a ductless range hood and one that vents to the exterior, permit-wise?

A ductless (recirculating) hood filters air and returns it to the kitchen—no exterior duct is needed. Aventura does not require a permit for installing a ductless hood as a replacement appliance on an existing circuit. An exterior-vented hood requires a Building Permit (or Building + Mechanical Permit depending on whether it's electric or gas-powered) because the duct installation involves cutting through an exterior wall, which is structural work. Exterior venting is more effective at removing humidity and odor, especially in Aventura's hot, humid climate, so many remodelers prefer it despite the added permit burden.

Can I do the electrical work myself, or do I need a licensed electrician?

You cannot. Florida Statutes Section 489.103 and Aventura's local amendments prohibit unlicensed electrical work in kitchens, even for owner-builders. You must hire a licensed Florida electrician (Class A or Class B, depending on scope). The city will not issue an electrical permit for unlicensed work, and if discovered, code enforcement can fine you $500–$1,000 and demand removal of all unpermitted circuits. Homeowner DIY exceptions apply only to low-risk work like replacing outlets or fixtures on existing circuits (no new circuits), and even that is heavily restricted. For kitchen remodels, assume you need a licensed electrician.

If my wall is non-load-bearing, do I still need an engineer's letter?

Yes, you must have a structural engineer confirm in writing that the wall is non-load-bearing before the city will approve wall removal. You cannot assume a wall is non-load-bearing based on appearance or because a neighbor's kitchen has a similar wall. A structural engineer's letter costs $300–$500 and is mandatory; many builders and contractors skip this step and face stop-work orders as a result. Have the engineer visit the property, inspect the wall alignment and floor framing above, and issue a signed letter stating 'This wall is not part of the load-bearing system' with supporting notes. Submit the letter with your building permit application.

How long does the permit review process take in Aventura?

Expect 3–5 weeks for full plan review. Aventura does not offer expedited over-the-counter plan review for kitchens (some jurisdictions do for small projects under a certain cost). The city's plan-review staff will check your drawings against the Florida Building Code, the IRC, and any local amendments. If there are deficiencies (missing GFCI details, vent routing unclear, load-bearing wall concerns), the reviewer will issue a correction list and you'll resubmit. The resubmission is then re-reviewed (another 2–3 weeks). To avoid delays, hire a experienced kitchen designer or contractor familiar with Aventura's code enforcement; they know the common pit-falls and will catch errors before submission.

What if I discover my kitchen was remodeled 10 years ago without permits—do I need to get permits now?

This is a common situation. If the prior unpermitted work is discovered during your current remodel permit application (e.g., the inspector notices altered framing or plumbing), you may be required to bring it into compliance with current code before the city approves your new permits. However, if the prior work is not discovered and you don't disclose it, you're not legally required to retroactively permit it UNLESS you're selling the home, refinancing, or making an insurance claim. At time of sale, Florida Real Estate Commission Form OP-U requires disclosure of permitted work—if your kitchen was unpermitted, you can disclose it as 'prior owner work, permits not available,' but this will raise buyer concerns and may reduce the home's value by 3–5%. Refinancing lenders often demand proof of kitchen-remodel permits; if you can't provide them, the lender may require a third-party inspection and re-permitting before closing. The safest move: contact the Building Department, explain the situation, and ask if the prior work can be 'grandfathered' (approved as-is) or if corrections are needed. Many jurisdictions allow grandfathering of old unpermitted work if it doesn't pose a safety hazard, but Aventura's policy varies by case—contact the chief building official's office to ask.

Do I need separate permits for plumbing and electrical, or is there one combined kitchen permit?

Aventura requires separate permits for Building, Plumbing, and Electrical. You'll file three applications and pay three permit fees (roughly $250–$400 each depending on project valuation). Some Florida cities bundle plumbing and electrical into the building permit, but Aventura maintains separate departments and separate fees. The advantage: you can coordinate inspections (e.g., rough plumbing and rough electrical can be requested on the same day, both inspected in one visit). The disadvantage: three separate applications, three separate fees, and three separate re-inspection fees if something fails. Expect the total permit cost to be $800–$1,300 for a typical kitchen remodel with plumbing and electrical changes.

Does Aventura require lead-paint disclosure for kitchen remodels in older homes?

Yes. If your home was built before 1978, any interior remodel work that disturbs paint on walls, trim, cabinets, or doors requires a lead-paint disclosure to the inspector before work begins. The city doesn't require EPA-certified lead abatement for kitchens (that's a federal requirement if you're selling the home or working with tenants), but you must disclose the presence of lead to the city and to anyone entering the home during construction. If you're removing old cabinets, walls, or trim, the contractor should use HEPA-vacuum containment to minimize dust. The disclosure is typically a one-page ORR (Office of Renovation Reform) Form filed with the permit application. Cost: $0, but failure to disclose can result in a $500–$1,000 city fine.

What inspections do I need to schedule, and in what order?

For a typical kitchen remodel with wall removal, plumbing relocation, and electrical changes, you'll schedule inspections in this order: (1) Framing (if walls are moved—engineer's letter is verified here), (2) Rough plumbing (before walls are closed), (3) Rough electrical (before drywall), (4) Drywall and final framing, (5) Final plumbing, (6) Final electrical, (7) Final building. If you have a gas range, add (8) Rough mechanical and (9) Final mechanical. If you have exterior range-hood venting, add rough and final mechanical as well. Schedule each inspection 24–48 hours in advance through the permit portal or by calling the Building Department. Inspections typically take 30 minutes to 1 hour. If an inspection fails, you'll be notified of deficiencies and can schedule a re-inspection after corrections are made (re-inspection fee: $75–$150 per sub).

Can I start work before my permits are approved, or do I have to wait for plan approval?

You must wait for all three permits (Building, Plumbing, Electrical) to be issued before any construction work begins. Starting work before permit approval is a violation of Florida Building Code and Aventura ordinance; the city can issue a stop-work order, fine you $250–$500 per day, and require removal of non-permitted work. Inspectors may show up unannounced to verify code compliance, and neighboring properties can file complaints if they see active construction without visible permit signage. The solution: plan your timeline to account for 3–5 weeks of plan review. If you're in a time crunch, hire an experienced permit expediter or contractor who knows the city's review staff and can identify deficiencies early, reducing re-review time. Cost: $200–$500 for expediting services, but often worth it to avoid project delays.

Disclaimer: This guide is based on research conducted in May 2026 using publicly available sources. Always verify current kitchen remodel (full) permit requirements with the City of Aventura Building Department before starting your project.